11th Street Local Bridge Lane Reductions To Occur December 26 Through January 14
Local Bridge Scheduled to be Completed Spring 2013
The District Department of Transportation (DDOT)
will reduce the 11th Street local bridge to one inbound lane and one
outbound lane on December 26, after the morning rush, to complete construction
work on the bridge deck.
There are currently two inbound lanes and one
outbound lane on the 11th Street local bridge. The lane reduction will
remain in place through January 14, 2013 while crews complete the bridge deck
construction. Once completed, the bridge will reopen to two lanes in each
direction and include the new 16-feet pedestrian and bicycle path that connects
to the Anacostia Riverwalk Trail.
For more information and to follow the bridge
project and AWI Program’s progress, please visit the 11th Street
Bridge project page of AnacostiaWaterfront.org. To join the project or AWI
community contact list or ask questions, please email ddot.awi@dc.gov or call 202-741-8528.